| 1 | List every load that may run at the same time. | Record each appliance or machine’s input watts from its nameplate. Example: lights, 0.20 kW; refrigerator, 0.30 kW; and a pump motor, 1.50 kW of rated mechanical output. Do not count equipment that will not operate simultaneously. | The total simultaneous running demand is the starting point. A motor’s output rating is not necessarily its electrical input; use nameplate input data where available. |
| 2 | Calculate motor starting surge separately. | A direct-on-line induction motor can draw several times its full-load current during startup; the actual value depends on motor design and starting method. For an illustration, a motor with 4× starting current has roughly 4× its running current-related starting demand. Check the motor nameplate or manufacturer data rather than treating this multiplier as universal. | Confirm the generator’s motor-starting or transient capability, not just its continuous kW rating. Starting demand is often expressed in kVA or current, so kW alone may not describe it. |
| 3 | Use kW and kVA correctly. | For a single-phase load, approximate running kVA as kW ÷ power factor. For a three-phase motor, use its rated voltage, current, and power factor. For example, 2.0 kW at a power factor of 0.8 is approximately 2.5 kVA. | Compare load requirements with both the generator’s rated kW and rated kVA. Check the stated power factor and whether the published rating is continuous, prime, or standby. |
| 4 | Check the largest-starting load and startup sequence. | Identify which motor starts while other loads are already running. If practical, start large motors one at a time and switch off nonessential loads during startup. A soft starter or variable-frequency drive can reduce starting demand when compatible with the equipment. | A sequential-start plan may avoid sizing for several simultaneous surges. Verify compatibility and follow the motor and control-system manufacturers’ instructions. |
| 5 | Allow for site conditions and load changes. | High elevation, high ambient temperature, long or undersized cables, and future equipment additions can affect available output or voltage performance. Use the generator manufacturer’s derating information for the installation site. | Choose a unit that can meet the calculated demand after applicable derating. Do not assume a fixed allowance applies to every generator or location. |
| 6 | Match voltage, phase, and operating duty. | Confirm whether the loads require single-phase or three-phase power and check voltage, frequency, and motor connection requirements. Estimate expected operating hours and distinguish continuous, prime, and standby use. | A generator with sufficient kW can still be unsuitable if its phase, voltage, frequency, or duty rating does not match the application. |
| 7 | Verify the complete load calculation before choosing rated kW. | Example method: add the electrical running input of all simultaneous loads; then evaluate the largest motor’s starting current or kVA while those other loads remain on. Compare both conditions with the generator’s continuous ratings and published transient response data. | Cylinder count alone does not determine usable output or motor-starting ability. Confirm ratings and starting performance in the manufacturer’s technical data, and consult a qualified electrician for uncertain or three-phase installations. |