| Applicable standard | Confirm the API 682 edition, seal category, arrangement, and qualification requirements specified in the purchase documents. | Project specifies API 682, 4th Edition; single seal, Arrangement 1. | Seal datasheet and vendor documentation identify the same specified edition and configuration. Do not assume an edition or arrangement that is not stated in the project documents. |
| Seal type and cartridge construction | Check that the assembly is supplied as a single cartridge seal and that its configuration matches the required arrangement and process service. | Single cartridge assembly; one seal set; process-side seal faces identified on the drawing. | Confirm the assembly description, sectional drawing, and datasheet agree. Verify any required containment or external support system separately. |
| Shaft or sleeve diameter | Measure the pump shaft or existing sleeve at the seal mounting location and compare it with the cartridge bore and approved pump drawing. | Pump sleeve: 50.00 mm nominal; cartridge bore: 50.00 mm nominal. | Confirm the specified fit, tolerances, surface condition, and any sleeve requirements on the approved drawings. Nominal values alone do not establish an acceptable fit. |
| Seal chamber bore | Check the seal chamber inside diameter and verify radial clearance for the cartridge components, including any centering or restriction features. | Measured chamber bore: 100.0 mm; cartridge outside envelope shown on drawing: 96.0 mm. | Compare measured dimensions and allowable clearances with the pump drawing and seal manufacturer's installation drawing. Confirm there is no interference throughout the assembly. |
| Chamber depth and seal setting | Verify the distance from the chamber face to the relevant internal shoulder or seal-seat location, and confirm the cartridge's setting dimension. | Chamber depth on pump drawing: 45 mm; cartridge setting dimension on installation drawing: 32 mm. | Use the drawing's stated datums and tolerances. Confirm the cartridge can reach its specified installed position without bottoming out or compromising the seal setting. |
| Gland dimensions and mounting | Compare the gland outside diameter, pilot or register, bolt pattern, bolt-hole size, and gasket interface with the pump seal chamber. | Gland register: 120 mm; four mounting holes: 14 mm diameter on a 150 mm bolt circle. | These are example values only. Verify the actual register, hole count, hole sizes, bolt circle, and gasket dimensions against the pump drawing; confirm the gland seats flat and concentric. |
| Axial and radial clearances | Check available space around the cartridge and rotating parts, including clearance to the shaft, sleeve, chamber, and adjacent pump components. | Drawing review records 2.0 mm nominal radial clearance at the identified cartridge envelope. | Verify the minimum clearance at worst-case tolerances and consider shaft movement, runout, and thermal effects as required by the project design. |
| Connections and orientation | Identify required flush, drain, vent, quench, or other connections and verify port size, thread or flange type, location, and orientation. | One 1/2 in NPT flush connection; port orientation shown at the top of the gland in the installation drawing. | Match the project piping plan and seal support-system requirements. Confirm that ports are accessible and that venting and drainage are practical for the installation. |
| Materials and process limits | Review face, elastomer, spring, and metal materials against the process fluid, operating temperature, pressure, and corrosion conditions. | Face pairing, elastomer designation, and wetted-metal grade listed on the seal datasheet; design limits stated separately. | Check material compatibility and stated operating limits against the process datasheet and project requirements. Do not infer suitability from a generic material description. |
| Seal datasheet and drawings | Obtain the completed seal datasheet, dimensional installation drawing, sectional drawing, and interface details. | Document register lists a datasheet, general arrangement drawing, sectional drawing, and installation instructions. | Ensure documents are revision-controlled and approved for the exact pump model, seal configuration, and supplied cartridge. |
| Setting devices and installation instructions | Confirm setting clips, spacers, or other shipment and installation devices are identified, with instructions for when to remove them. | Setting clips shown in the drawing; removal step included in the installation procedure. | Verify the documented setting method and installation sequence. Do not remove setting devices until the specified installation step. |
| Testing and quality records | Review the required inspection, test, material, and traceability records specified by the purchase order and applicable API 682 provisions. | Inspection and test plan identifies required checks; material certificates and final inspection records listed for submission. | Confirm the records meet the contract and project quality requirements. Test scope and acceptance criteria should be taken from the applicable standard and purchase documents. |
| Final fit-up confirmation | Record measured pump interfaces and compare them with the approved seal drawing before installation. | Checklist records shaft/sleeve diameter, chamber bore and depth, gland register, bolt pattern, and port orientation. | Resolve any mismatch with the responsible engineering parties before installation; do not modify the cartridge or pump interfaces without approved instructions. |